In this article you will learn:
What is Auto stagger?
How do I select projects and teams?
How do I run Auto stagger?
What happens to my projects?
1. What is Auto stagger?
Auto stagger schedules several planned projects automatically, so that they fit around the capacity of the teams you choose. It is available in Simulation mode, and you can stagger up to 50 projects at once.
2. How do I select projects and teams?
Only planned projects with a due date can be selected. Projects that are already in progress (any status other than Planned or Not set), projects without a due date and projects in excluded scenarios are disabled. Hover over a disabled checkbox to see why.
Tick the checkbox at the top of the project list to select the first 50 projects, or tick individual projects.
Click the teams icon and tick one or more teams.
Click the date picker icon and select the earliest start date for the staggered projects. If you do not select a date, the earliest start date is next week.
3. How do I run Auto stagger?
Click Auto stagger at the bottom of the screen.
Keep the tab open while Auto stagger runs. If you close the tab or reload the page, the action is cancelled. To leave the Auto stagger area without staggering, click the cancel icon. It closes the area and clears all selections.
4. What happens to my projects?
Projects are staggered in the order of the project list. The project at the top has the highest priority. Auto stagger aims for a team utilisation of 80% to 100%. If a project is booked beyond a team's capacity, the team may be overbooked.
Staggered projects are shown with a yellow background.
When staggering is complete, all projects are deselected again. If a project could not be staggered, a message appears in the project header beside the Auto stagger checkbox. Hover over the message to see the project name and the reason, for example that a project in progress cannot be staggered. Selecting the Auto stagger checkbox again hides the message.